Downtown Newport Richey Sidewalk and Street Improvements

This project encompassed six city blocks in the downtown area of the City of New Port Richey; along Grand Boulevard from Main Street to Delaware Avenue.  It included the removal and reinstallation of the storm water and domestic water systems.  It also included the removal and reconstruction of the sidewalks, drives, parking slabs and curbs along both sides of Grand Boulevard.  The curb side of the sidewalks were lined with brick pavers.  Decorative street lights and trees with irrigation was provided to add beauty to the project.  This project was under taken during normal hours of operations for the restaurants and shops in the areas with very little interruption to the businesses

 

PROJECT INFORMATION

Project:              Downtown Sidewalk and Street Improvements Phase II                                           

Location:           New Port Richey, FL

Owner:              City of New Port Richey                

Owner’s Rep:   Ernie Denny

Phone:               (813)841-4517

Type:                               Streetscape/Sidewalks

Construction Area:      6 city blocks

Capacity:                       General Contractor

Contract Value:            $828,585.20

Contract Type:             Unit Price Bid

Architect/Engineer:      C & D Engineering

Completion Date:         October, 1995